May 14, 2025
- Kristin Manning
- May 14
- 1 min read
On April 29, we had the sheet rock delivered and ready for installation.
The exterior of the house looks amazing now that the brick veneer has been placed on the front. The metal roofing was also installed on the water tables.
Inside the home, the spray foam insulation process began on May 9th.
On Mother's Day, the family visited the house and wrote Bible verses on the framing.
Once the spray foam was inspected on May 12, it was on to sheetrock installation! This has been the most exciting change to see. The installation is not finished yet, but a huge amount of progress was made yesterday.